Applied Digital adds AI data-center lease worth about $5.4 billion
The 150 MW, 18-year lease improves rental pricing while construction consumes cash before delivery begins. We expect long-term debt minus unrestricted cash to exceed $3,314.0 million for the fiscal quarter ending 30 November 2026.
An electricity rate approval stands between Applied Digital and draws on a $300 million construction bridge for Delta Forge 1. On 23 November 2026, the company also announced an 18-year lease for 150 MW of AI data-center capacity, worth $5.4 billion over its base term. Its draw conditions expose the business: somebody pays to build facilities and secure power before rent begins.
We expect Applied Digital's long-term debt minus unrestricted cash to rise above $3,314.0 million in the fiscal quarter ending 30 November 2026, and put the odds at about two in three. Lease Before Cash describes the interval between a signed tenant and the rental income that finances its building. At 31 August 2026, $6,263.9 million of long-term debt less $2,949.9 million of unrestricted cash equaled $3,314.0 million. The next report measures the aggregate financing burden, including campuses under development before the new lease was signed.
Spread $5.4 billion over 150 MW and 18 years, and the new rent averages about $2.0 million per MW-year, versus about $1.65 million from Delta Forge 2's $5.2 billion over 210 MW and 15 years. That is roughly 21% more gross rent per unit of capacity. Management has improved the future rental stream available to service debt. The premium leaves more prospective rent for builders and their creditors to divide.
The latest agreement takes company-wide contracted base-term lease revenue above $41 billion, about 75% of it with investment-grade customers. If every option is exercised, this lease alone reaches about $12.7 billion over 33 years. Long leases give lenders decades to recover their money. Delivery of the new capacity is currently anticipated to begin in the first half of 2028, subject to development milestones, utility arrangements and regulatory approvals. Contractors require cash for construction well before the tenant's rent begins.
In the quarter ended 31 August 2026, property and equipment purchases consumed $2,074.7 million against $63.9 million generated by operations. Borrowings of long-term debt brought in $1,648.5 million in that same period. These were company-wide flows from the existing development portfolio, separate from the newly signed lease. They show the scale of capital required to turn contracts into buildings, financed with claims on future rent.
That August quarter also delivered revenue of $341.9 million, up 322%, and adjusted EBITDA of $64.4 million. Interest expense reached $77.4 million and the net loss attributable to common shareholders was $221.0 million. Revenue grew dramatically while financing costs consumed a greater amount than adjusted EBITDA. The gap between commercial expansion and internal funding is the reason the next balance sheet matters more than the latest lease total.
A project financier would look at the same lease and see a way through the funding squeeze. Applied Digital CFO Saidal Mohmand says the sequence begins with "first-in equity already funded from our balance sheet", uses the $5 billion programmatic equity partnership with Macquarie Asset Management and ends with long-term project financing supported by leases. At 31 August, Applied Digital had $2,949.9 million of unrestricted cash and $313.4 million of restricted cash. An investment-grade tenant and a 21% rental premium strengthen the revenue side of a lender's calculations. Funding through project equity can preserve the parent's cash while buildings advance.
The Form 10-Q for the quarter ended 31 August 2026 makes the case sharper. Applied Digital "generally has the right to cancel open purchase orders prior to delivery or terminate the contracts without cause". It can slow construction rather than draw debt on unattractive terms. A subsidiary also closed $1.59 billion of senior secured notes at par, carrying 7.000% interest and due 2031, to fund a 150 MW building at Polaris Forge 1. This is one completed financing at scale. With those tools, the opposing case for the quarter ending 30 November is that cash conservation can hold debt less unrestricted cash at or below the August benchmark.
The completed bond is both a financing victory and a warning for common equity. In the quarter when it closed, the company bought $2,074.7 million of property and equipment and borrowed $1,648.5 million of long-term debt. Long-term debt rose from $4,959.5 million on 31 May 2026 to $6,263.9 million on 31 August 2026. Secured creditors funded a real building, and the company still finished with a larger debt balance. An equity partner or postponed purchase orders offer relief, but existing construction keeps demanding capital.
The company's previous large lease offers a narrower lesson about the stock. Delta Forge 2's $5.2 billion contract was announced on 8 June 2026. Shares closed at $40.945 that day, $41.91 on 9 June, $38.92 on 10 June and $11.49 on 20 November 2026, a 72.6% fall from 9 June. That sequence is one illustration of why contract value alone offers weak protection for equity prices, rather than evidence about the cause of the decline. This lease improves on Delta Forge 2's gross rent per MW-year by about 21%, so its operating promise is greater.
At 8:54 a.m. ET on 23 November 2026, APLD was quoted at $12.97 in premarket trading, up 12.88% from its $11.49 close on 20 November 2026. The quote followed a better-priced lease; equity remains the residual after lenders and project partners. Customer concentration sharpens that distinction. In the August quarter, Customers A, B and C accounted for 56%, 21% and 11% of revenue. A handful of high-quality tenants can make debt easier to raise while giving those tenants a prominent place in the revenue stream.
A fund manager should avoid adding unhedged APLD common at that $12.97 quote ahead of the 11 January 2027 fiscal Q2 10-Q. That price sits against $6,263.9 million of reported long-term debt at 31 August and an August quarterly net loss to common owners of $221.0 million. The next reported funding position matters, followed by terms on permanent project debt. Big contract totals bring lenders to the table; the terms decide how much remains for the equity.
Management expects financing for Delta Forge 1 and Polaris Forge 3 in the first calendar quarter of 2027, followed by Delta Forge 2 in the second. The $300 million Delta Forge 1 bridge is a 364-day delayed-draw facility at SOFR plus 300 basis points, with draws conditioned on milestones, covenants, lender consents and state approval of electrical rates. Each approval brings the construction timetable closer to the lender's funding calendar. Lease Before Cash ends when the building earns rent; the capital obligations will still be there when it does.
We would pass on APLD common at the $12.97 premarket quote until the next reported debt less unrestricted cash figure stops climbing. We would be wrong if the fiscal Q2 2027 Form 10-Q, due 11 January 2027, shows long-term debt minus unrestricted cash unchanged at $3,314.0 million or below it for the quarter ended 30 November 2026.